Client: The Environment agency
Engineer: The Halcrow Group Ltd
Main Contractor: John Mowlem & Co

The main contract was to demolish and reconstruct the walkway,
refurbish the existing buck gates and lifting gear, construct reinforced concrete apron, wing walls, fish pass support structure and pre-barrages. Including stonework and brickwork. Also works to the weir island.

LG Kimber Engineering responsibilities;
Dismantle, refurbish and re-install the gates and lifting gear. Including shot blasting, galvanising and painting plus fitting new seals and guides. Refurbish the A frames. Supply and install walkway framework Fabricate and install galvanised mild steel baffle plates, debris deflector, larnier and eel passes.